COURT: CONTRACTORS CAN LIEN FOR EXTRA WORK THAT WASN’T PART OF A WRITTEN CHANGE ORDER

Date: March 20th, 2014

In a decision issued on Monday, March 10, the state Court of Appeals clarified an unsettled provision of the lien statute, holding that contractors can lien for extra work not incorporated by written change order into the contract. The relevant facts of the case are … Read More »

AGC SUPPORTS EMPLOYER IMMUNITY FROM SUIT IN SUPREME COURT

Date: March 4th, 2014

A pending lawsuit against The Boeing Company threatens to impose new liability on Washington contractors whose employees have been exposed to toxic or harmful substances on a jobsite. The case involves employer liability for asbestos exposure 28 years ago, but the outcome of the case … Read More »